Polaris Forge 1 Campus Update | November 2025
Автор: Applied Digital
Загружено: 2026-01-08
Просмотров: 287
Описание:
Winter has arrived in full force, but so has the commitment of the crews building Polaris Forge 1. Their resolve is why this campus continues to reach major milestones on schedule.
Building 1 (100 MW Critical IT Load): Both phases of Ready-for-Service are complete. Data halls have been turned over to the tenant, marking the transition from construction to activation. Integrated Systems Testing has also been completed, confirming facility reliability. In recognition of the teams on site, crews organized a turkey giveaway to thank every worker contributing to this project.
Building 2 (150 MW Critical IT Load): Progress continues across both interior and exterior scopes. Slab-on-grade pours are underway, the first CAT generator has been installed, and sitework concrete, utilities, and roof work are advancing in parallel. Two-shift construction begins in early December to maintain momentum through winter, with a winter-ready roof enclosure entering fabrication to keep progress uninterrupted.
As temperatures drop, the commitment of our teams only rises, and Polaris Forge 1 continues moving toward the future it was built for.
Subscribe for ongoing AI Factory construction updates and infrastructure insights.
Learn more at https://www.applieddigital.com/
#PolarisForge1 #AppliedDigital #AIInfrastructure #DataCenters #AIFactories #HighPerformanceCompute #APLD
Повторяем попытку...
Доступные форматы для скачивания:
Скачать видео
-
Информация по загрузке: