In todays video, i’m excited to share with you the full comprehensive breakdown of putting up a structural 4-Bedroom Apt. from scratch. Due to funding limitations, this project spanned from June 26, 2023, to January 15, 2025.
To manage the project efficiently, we divided it into two distinct phases:
Phase 1: Setup to Lintel Stage
Phase 2: Lentil to Roofing Course
Find Below the Estimates;
Complete Structural Cost
5” Hollow Blocks : 3,100 PCS = 21,670 GHS
58 Bags of 32.5r Cement (Block Laying) = 4,708 GHS
35 Bags of 42.5r Cement (Concrete Works) = 3,275 GHS
Block Laying Workmanship = 8,740 GHS
Concrete Works Workmanship = 4,050 GHS
2 Trips of Sand = 5,400 GHS
1 Trip of stones = 2,800 GHS
14MM Rod : 24 PCS = 1,980 GHS
12MM : 68 PCS = 4,764 GHS
3/8MM : 32 PCS = 599.5 GHS
Binding Wire : 3 Coil = 230 GHS
Steel Bender’s Workmanship = 2,250 GHS
Wood : Cyber Board + Bush Cut = 5,035 GHS
Nails (4”,3”,W.Nail) = 900 GHS
Carpenter’s Workmanship = 3,600 GHS
Miscellaneous & T&T = 2,590 GHS
Water Fetched = 225 GHS
TOTAL : 72,816.5 GHS
Cost Breakdown by Phases;
Phase 1 (ONLY) - Setup to Lentil Stage
5” Hollow : 1,700 PCS X6.5 : 11,050 GHS
Cement (32.5r): 20 Bags X72 : 1,440 GHS
Cement (Gacem 42.5r) : 20 Bags X97&80: 1,685 GHS
Miscellaneous : 730 GHS
Continual Pillars : 14MM (24) X82: 1,968 GHS
3/8 : 10PCS X16 : 160
Binding Wire 1 : 70
Steel Bender Workmanship: 900
Wood for Lentil + T&T (25)X85: 2,350
Carpenter Labor(Pillars + Lentil): 1,400
Nails : 450 GHS
Mason + Laborer Block Laying : 3,260
Mason + Laborer Concrete : 1,350
Other T&T : 200
TOTAL for Setup to Lentil Stage: 27,025 GHS
Phase 2 (ONLY) : Lentil To Roofing Course
12mm : 30 X 65.60 = 1,968 GHS
12mm : 38 X 73.60 = 2,796 GHS 🔺
3/8mm : 10 X 17.50 = 175.50 GHS
3/8mm : 12 X 22 = 264 GHS 🔺
Binding Wire : 2 Coil = 160 GHS
Steel Bender Workmanship : 1,350 GHS
Cyber Board : 25 X 85 + Cutting : 2,350 GHS
Bush Cut : 7 X 80 GHS : 560 GHS
Nails : 4”(2), 3”(3) X 70 : 450 GHS
Carpenter : 2,200 GHS
Cement (42.5r) : 15 X 106 = 1,590 GHS
Cement (32.5r) : 38 X86 = 3,268 GHS
Lentil Concrete Casting : 2,700 GHS
Blocks Laying Labor: 5,480 GHS
5” Blocks(2) : 1,000 X 7.5 = 7,500 GHS
5” Blocks(2) : 400 X 7.8 = 3,120 GHS GHS
Sand : 2 Trips = 5,400 GHS
Stones : 1 Trip = 2,800 GHS
Miscellaneous : 1,000 GHS
T&T : 660 GHS
Water : 225 GHS
Total : 45,791.50 GHS
GROSS TOTAL : 72,816.5 GHS
Mason’s Contact
Name: Mr. Attah (Mason)
Phone Number: 0555434760
Thank you for Watching!