A major milestone is complete on the Downtown Rail Reconstruction Project! 🚊✨
RTD has officially wrapped up its 86-day reconstruction of the light rail crossing at Kalamath Street and Colfax Avenue right on schedule.
Here’s what crews accomplished:
🔧 Rebuilt the entire crossing from the ground up
🚉 Replaced 1,300 feet of track
🔀 Installed 1,100 feet of special trackwork
🚗 Reconstructed one vehicle crossing
🚶♀️ Upgraded two pedestrian crossings
💼 Advanced a key piece of RTD’s $152 million investment to modernize aging track and deliver a smoother, more reliable ride
This work sets the stage for what’s next:
🛠️ Reconstruction along Colfax Avenue (beginning 2026)
🔄 Additional Downtown Loop track replacements
📐 Continued design work along Welton Street
RTD will keep sharing updates as the next phases take shape.
Stay tuned and follow the progress at rtd-denver.com/railproject.