Update 27
The works along Section 1 is moving at a moderately fast pace. The Buendia area is really busy as high columns are erected beside the Buendia Flyover and PNR line. As for Osmena Hwy from Buendia flyover to Pablo Ocampo there are not much updates, what is really noticeable was from Pablo Ocampo towards Jollibee / Quirino Avenue as the girders are in place. As for section 3 and section 4 there are new developments specially the Sgt Rivera segment.
We have consolidated two months to see changes. But since many were requesting for a monthly will be returning to monthly update. Apologies for the delay in posting as it has been a toxic and busy April for me. Some followers knew what happened :-) i am alright now thank you for the concern.