HK’s manhole rehabilitation solution, Monoform PLUS™, reinforced the underground infrastructure below train tracks and prevented a train derailment at an industrial facility. Learn more: hksolutionsgroup.com/PreventStructuralCollapse
Three manholes at a food processing plant were in a state of complete failure, one positioned below two sets of railroad tracks. The HK team acted quickly to find an ideal solution that would not disrupt the plant’s operations and could be completed before a structural collapse caused a sewer backup and train derailment. From start to finish, the project was completed in three weeks.
Monoform PLUS™ is an innovative, trenchless manhole rehabilitation solution that is 100% structural and 100% corrosion-resistant to protect sewer structures exposed to corrosive environments just like the environment at the plant.
Read more about HK’s manhole rehabilitation solutions: hksolutionsgroup.com/ManholeRehabilitation
Download our underground infrastructure checklist: hksolutionsgroup.com/UndergroundInfrastructureChecklist
TIMESTAMPS
00:00 Manhole Rehab Prevents Collapse
00:15 Manhole Inspection Begins
00:27 Remove Manhole Cast
00:46 Remove Debris From Manhole
01:27 Install Pipe Slips & Set Manhole Base Form
01:37 Measure HDPE Manhole Liner
02:22 Place Monoform™ Forming System
02:44 Install HDPE Manhole Liner
03:25 Reinforced Underground Infrastructure
03:52 Pour Monolithic Concrete Liner
04:31 Set Sewer Casting
05:07 Before and After Manhole Rehab