Ausdecom Ford Geelong Press Plant
Автор: Ausdecom
Загружено: 2022-05-11
Просмотров: 7138
Описание:
Ausdecom dismantled a series of redundant plant and equipment inside the former Ford Manufacturing Plant.
Over two phases, 27,700 man hours and specialist equipment, works included the safe internal demolition of all equipment within the former Ford Manufacturing Facility.
Safely engineering and completing the mechanical demolition of all redundant plant equipment ready for refit out and construction works to redevelop the site
Asbestos removal to all former equipment prior to demolition
Demolition of 19 redundant hydraulic presses within press plant
Controlled cutting and lifting of press cushions and associated support beams over sub-floor equipment within 13 independent press lines
Demolition of all internal equipment within Engine Plant Building, Barra Heads, and Tool Grind area
Demolition of redundant outside gantry crane and rail system
10,500 Tonne scrap metal removed
#demolition #recycling #ford