🏗️ Q2 2025 Construction Update – Yas Golf Collection
📍 Yas Island, Abu Dhabi
Progress across all 5 phases of Yas Golf Collection by Aldar is moving rapidly — with Phase 1 already ready for handover, and other phases close behind! This smartly designed, lifestyle-focused community is rising next to Yas Golf Links and Yas Bay’s most vibrant offerings.
⸻
🏡 Phase 1 – 99% Complete
• Building Completion Certificates (BCC) obtained
• Power & water connected
• Snagging completed
• Furniture delivery in progress
🔜 Handover to customers starting soon
⸻
🏢 Phase 2 – 97% Complete
• Landscaping, testing & commissioning done
• 80% joinery complete
• Snagging and inspections in progress
🔜 BCCs and furniture installation next
⸻
🌿 Phase 3 – 91% Complete
• Façade & second-stage MEP complete
• 65% landscaping, 40% joinery
🔜 Final finishes, tree planting & approvals underway
⸻
🏗️ Phase 4 – 83% Complete
• Infrastructure works & 90% façade complete
• 80% internal finishes & shallow MEP
🔜 Final MEP, joinery & landscape works starting
⸻
🏘️ Phase 5 – 75% Complete
• Deep infrastructure & 80% façade complete
• 60% internal finishes & MEP
🔜 Road preparation & MEP final stages next
⸻
📞 For unit availability or updates: +971505231194
⸻
#YasGolfCollection #YasIsland #AldarProperties #ConstructionUpdate #AbuDhabiRealEstate #OffPlanUAE #LuxuryApartments #GolfLiving #UAEHomes #RealEstateUAE #NearHandover #YasLinks
Повторяем попытку...
Доступные форматы для скачивания:
Скачать видео
-
Информация по загрузке: