LRT3 main contractor liable for RM474.8mil in late penalties, says Loke
Автор: The Star
Загружено: 2026-03-02
Просмотров: 2716
Описание:
The main contractor for the LRT3 project is liable to pay Liquidated and Ascertained Damages (LAD) amounting to RM474.8mil as of Dec 31 last year.
Transport Minister Anthony Loke said the figure was calculated based on the stipulated daily LAD rate of RM2.7mil imposed on the contractor for each day of delay.