patna metro project update | Patna Metro depot | Patna Metro work progress | Patna Metro office@Dugu
Автор: DP NEWS
Загружено: 2021-06-06
Просмотров: 844
Описание:
हेलो सर
मैं डुगू आपका स्वागत करता हु अपने चैनल में, मैं अपने यूट्यूब चैनल में बिहार तथा इंडिया के विभिन्न जगहों के घूमने , शॉपिंग, इत्यादि इसके साथ साथ ये भी बता हू की आप उस जगह कैसे जायेंगे और कितना किराया आपको देना होगा इन सभी का वीडियो अपने ब्लॉग के माध्यम से बताता हु ताकि आप कभी भी यह आया तो दिक्कतों का सामना कम से कम हो था हमारे देश में ट्यूरिस्ट की संख्या बढ़ सके
_____________________________________________________________________________________________
Hello sir,
I welcome you to my channel, in my YouTube channel, I will visit various places in Bihar and India for shopping, shopping, etc. Also tell you how you will go to that place and how much fare you will have to pay. I tell you the video through my blog so that if you ever came to it, the problems could be minimized, in our country the number of Turist could increase.
_______________________________________________________________________________________________
#Patna_Metro_Station_list
#Patna_Metro_Map_More_results
#patna_metro_latest_update
patna_metro_latest_update
------------------------------------------------------------------------------------------------------------------------------------
Status update
A Detailed Project Report (DPR) was to be prepared by May 2015.
February 2016: The Bihar cabinet approved the DPR for Patna Metro prepared by RITES, with a budget of ₹16,960 crore and planned to be executed under a PPP model by 2021.
May 2016: The Patna Metro Rail project got a fresh boost when union urban development minister M Venkaiah Naidu reportedly assured the government of Bihar of the in-principle approval of the project within a month.
3 July 2018: Bihar chief secretary Deepak Kumar approved the proposed Patna Metro Rail's revised DPR,[2] with a revised estimated cost of ₹ 19,500 crore, including land acquisition costs.
20 Sep 2018: RITES submitted the revised DPR to the Urban Development and Housing department.
25 Sep 2018: The Bihar cabinet approved the constitution of "Patna Metro Rail Corporation Ltd (PMRCL)" as a Special-Purpose Vehicle (SPV) for the implementation of the metro rail project in the capital.
28 Sep 2018: The Public Finance Committee approved the DPR of the Patna Metro Rail Project.
9 Oct 2018: The Bihar cabinet approved the DPR, after which it is to be sent to the central government for approval.
20 Nov 2018: The Central Government approved the DPR for Patna Metro.
6 Feb 2019: Patna Metro received approval from the Public Investment Board (PIB)
13 Feb 2019: The Union Cabinet approved the Patna Metro Rail Project comprising two corridors.
17 Feb 2019: Prime Minister Narendra Modi laid the foundation stone for Patna's first metro rail corridor.
4 March 2019: Patna Metro Rail Corporation Limited formally opened its office at Indira Bhavan.
25 Jul 2019: Patna Metro work set to start in three months.
23 Aug 2019: Drone survey started and is slated to end on 15 October.
4 Sep 2019: DMRC to oversee project execution. Work to begin by the end of 2019.
18 Nov 2019: CEG starts soil testing.
28 Feb 2020: AECOM bags consultancy contract for both corridors for the Patna Metro Project.
23 July 2020: Quality Buildcon emerges as the lowest bidder for constructing the New ISBT Depot on Line 2
31 August 2020: NCC emerges as the lowest bidder for the first 6.1 km of the route's construction (Malahi Pakri to New ISBT of Line 2)
18 September 2020: Delhi Metro Rail Corporation invites bids for the construction of the first package of Patna Metro’s Line-1.
18 September 2020: Delhi Metro Rail Corporation invites bids for the construction of the first underground package of Patna Metro’s 14.05 km
17 November 2020: Six firms submit bids for Patna Metro's substation and cabling works for 30.91 km Phase 1.
20 November 2020: Four firms submit bids to build the elevated portion of the 8 km package of Patna Metro Phase 1's 16.86 km Line 1
26 November 2020: Physical construction on Patna Metro's Phase 1 officially begins.
21 December 2020: Delhi Metro Rail Corporation (DMRC) invites bids for the supply and commissioning of 1200 MT of regular rails at the New ISBT Depot for Phase 1 of Patna Metro.
14 January 2021: Four bidders emerge for Patna Metro's 14.05 km underground section of Line-2.
5 February 2021: Nine firms submit bids for electrical and mechanical systems of Patna Metro's 30.91 km Phase 1
5 March 2021: Five firms submit bids for the standard-gauge ballasted track work contract of Patna Metro's New ISBT Depot
16 April 2021: Voestalpine VAE VKN India Pvt. Ltd. and Vossloh Cogifer S.A. emerge as only firms to submit bids for supplying UIC-60 turnouts and scissor crossovers for Patna Metro's Phase 1
28 April 2021: Pier work begins on Patna Metro's 6.107 km Malahi Pakri—New ISBT
----------------------------------------------------------------------------------------------------------------------------------------------------------