Free Float vs Total Float in Project Management
Автор: Brandan Jones
Загружено: 2024-07-28
Просмотров: 718
Описание:
Total Float and Free Float are easy topics to confuse in Project Management. In this video, I make sense of them with an example.
Total Float: this path of tasks can be delayed by this amount before impacting the finish date of the project.
Free Float: This task can be delayed by this amount before impacting the early start date of the next task. In almost all cases, that next task has at least two predecessors, and one of the predecessors is longer than the predecessor with free float. The difference in the time to complete these two predecessor tasks is, effectively, free float.
#projectmanagement #freefloat #totalfloat #criticalpath