MDTA: Remaining Key Bridge structures to be demolished in July
Автор: WBAL-TV 11 Baltimore
Загружено: 2025-06-26
Просмотров: 2677
Описание:
Demolition of the remaining structures from the Key Bridge collapse will begin next month, according to the Maryland Transportation Authority. The demolition process is set to begin around July 7, weather permitting, according MDTA Executive Director Bruce Gartner. The process is expected to take around nine months to complete. Those who live near the site of the bridge should expect typical construction project noise from 7 a.m. — 7 p.m. and numerous tug and barge operations, Gartner said. Buoys will also be out in the water to mark safety zones and no entry areas.