Ahmednagar-Beed-Parli Vaijnath New Rail Line update Maharashtra Ashti Solapurwadi Amalner Vighanwadi

Автор: Map Rail India

Загружено: 2025-07-26

Просмотров: 3497

Описание: The Ahmednagar-Beed-Parli Vaijnath New Railway Line (261.25 km) is a key Maharashtra project, boosting Marathwada's connectivity. Cost-shared 50:50 by GoI & GoM.

ahmednagar
ahmednagar beed parli railway line
ahmednagar to beed railway

Progress:
Ahmednagar-Narayandoh (12.27 km): Mar 29, 2017
Narayandoh-Solapurwadi (23.26 km): Feb 25, 2019
Solapurwadi-Ashti (30.64 km): Dec 31, 2021
Ashti-Amalner (33.92 km): Jan 5, 2024

Vighanwadi-Beed (34.85 km): Inspected Feb 2025 (Beed-Ahmednagar route ready).
Overall, 132.92 km commissioned by Sep 2024; Ahmednagar-Beed (169 km) by Apr 2025.
Physical progress: 78% overall (early 2025), with 99% land acquisition.

Completion Target: December 31, 2025.

Proposed Stations (25 total):
Parli Vaijnath,
Tokwadi,
Nagapur,
Sirsala,
Telgoan,
Wadwani,
Ghatsawali,
Mauj,
Beed,
Talegan,
Rajuri,
Hiwarsinga,
Raimoha,
Vighanwadi,
Jatnandur,
Amalner,
Hatola,
Wavi/Wetalwadi,
New Ashti,
Kada,
New Dhanora,
Solapurwadi,
New Loni,
Narayandoho,
Ahmednagar Junction.

This line will significantly enhance regional growth.
#Ahmednagar #Beed #ParliVaijnath #RailwayProject #Maharashtra #IndianRailways #Infrastructure

Marathi (अक्षरे: ९३८)
अहमदनगर-बीड-परळी वैजनाथ नवीन रेल्वे लाईन (२६१.२५ किमी) हा महाराष्ट्रातील महत्त्वाचा प्रकल्प आहे, जो मराठवाड्याची कनेक्टिव्हिटी वाढवेल. भारत सरकार आणि महाराष्ट्र सरकार ५०:५० खर्च वाटून घेत आहेत.

प्रगती:
अहमदनगर-नारायणडोहो (१२.२७ किमी): २९ मार्च २०१७
नारायणडोहो-सोलापूरवाडी (२३.२६ किमी): २५ फेब्रुवारी २०१९
सोलापूरवाडी-आष्टी (३०.६४ किमी): ३१ डिसेंबर २०२१
आष्टी-अमळनेर (३३.९२ किमी): ५ जानेवारी २०२४

विघनवाडी-बीड (३४.८५ किमी): फेब्रुवारी २०२५ मध्ये तपासणी (बीड-अहमदनगर मार्ग तयार).
एकूण, सप्टेंबर २०२४ पर्यंत १३२.९२ किमी कार्यान्वित; एप्रिल २०२५ पर्यंत अहमदनगर-बीड (१६९ किमी) कार्यान्वित.
शारीरिक प्रगती: ७८% (२०२५ च्या सुरुवातीला), ९९% भूसंपादन पूर्ण.

पूर्ण होण्याची अंतिम तारीख: ३१ डिसेंबर २०२५.

प्रस्तावित स्थानके (एकूण २५):
परळी वैजनाथ,
टोकवाडी,
नागपूर,
सिरसाळा,
तेलगाव,
वडवणी,
घाटसावली
, मौज,
बीड,
तळेगाव,
राजुरी,
हिवरसिंग,
राईमोहा,
विघनवाडी,
जातनंदूर,
अमळनेर,
हाटोला,
बावी/वेतलवाडी,
नवीन आष्टी,
कडा,
नवीन धानोरा,
सोलापूरवाडी,
नवीन लोणी,
नारायणडोहो,
अहमदनगर जंक्शन.

ही रेल्वे लाईन प्रादेशिक विकासात मोठी भर घालेल.

#अहमदनगर #बीड #परळीवैजनाथ #रेल्वेप्रकल्प #महाराष्ट्र #भारतीयरेल्वे #पायाभूतसुविधा

Hindi (अक्षर: ८७६)
अहमदनगर-बीड-परळी वैजनाथ नई रेलवे लाइन (२६१.२५ किमी) महाराष्ट्र की एक प्रमुख परियोजना है, जो मराठवाड़ा की कनेक्टिविटी बढ़ाएगी। भारत सरकार और महाराष्ट्र सरकार ५०:५० लागत साझा कर रहे हैं।

प्रगति:

अहमदनगर-नारायणडोहो (१२.२७ किमी): २९ मार्च २०१७

नारायणडोहो-सोलापूरवाडी (२३.२६ किमी): २५ फरवरी २०१९

सोलापूरवाडी-आष्टी (३०.६४ किमी): ३१ दिसंबर २०२१

आष्टी-अमळनेर (३३.९२ किमी): ५ जनवरी २०२४

विघनवाडी-बीड (३४.८५ किमी): फरवरी २०२५ में निरीक्षण (बीड-अहमदनगर मार्ग तैयार)।
कुल मिलाकर, सितंबर २०२४ तक १३२.९२ किमी चालू; अप्रैल २०२५ तक अहमदनगर-बीड (१६९ किमी) चालू।
भौतिक प्रगति: कुल ७८% (२०२५ की शुरुआत में), ९९% भूमि अधिग्रहण।

पूरा होने का लक्ष्य: ३१ दिसंबर २०२५।

यह लाइन क्षेत्रीय विकास को महत्वपूर्ण रूप से बढ़ाएगी।

#अहमदनगर #बीड #परळीवैजनाथ #रेलवेप्रकल्प #महाराष्ट्र #भारतीयरेलवे #बुनियादीढांचा

April 2025, the Ahmednagar – Beed section (169 km) has been commissioned. Work is now actively focused on the remaining sections towards Parli Vaijnath.

Physical Progress & Resources: The project shows impressive overall physical progress of 78% as of early 2025. This includes:

Earthwork: 97.40% completed.

Major Bridges: 77% (49 out of 64) completed.

Minor Bridges: 83% (250 out of 301) completed.

Road Over Bridges/Road Under Bridges: 65% (126 out of 195) completed.

Ballast supply: 87% completed.

Track linking: 41% (118.38 km out of 285.89 km) completed.

Power line crossings: 91% completed.

Land Acquisition: Land acquisition for the project is nearly complete, reaching an impressive 99%, with 1821.56 hectares secured out of 1806.19 hectares required, indicating minimal hurdles remaining in this critical area.

Financial Investment: The project has an allocated budget of ₹4805.17 Crore (as of November 2023 updates), with ₹3699 Crore already spent. Central Railway's overall expenditure for multitracking projects (including new lines, doubling, 3rd/4th lines) was ₹2983.47 Crore in the current fiscal year (as of Nov 2023).

Project Completion Timeline:

The latest official update from India Investment Grid on July 4, 2025, sets the Project Completion Date as December 31, 2025, for the entire Ahmednagar-Beed-Parli line.

Impact:
This new railway line is poised to revolutionize connectivity in the Marathwada region.

The project, which was initially sanctioned in 1995-96 but received approval for its current form in November 2015, has gained significant momentum, with direct monitoring by the Prime Minister's Office (PMO) in earlier phases.

Не удается загрузить Youtube-плеер. Проверьте блокировку Youtube в вашей сети.
Повторяем попытку...
Ahmednagar-Beed-Parli Vaijnath New Rail Line update Maharashtra Ashti Solapurwadi Amalner Vighanwadi

Поделиться в:

Доступные форматы для скачивания:

Скачать видео

  • Информация по загрузке:

Скачать аудио

Похожие видео

Maharashtra New Rail Lines Central Railway Projects Mumbai Pune Bhusawal Solapur Nagpur Akola Wardha

Maharashtra New Rail Lines Central Railway Projects Mumbai Pune Bhusawal Solapur Nagpur Akola Wardha

Одесса на Связи!!!

Одесса на Связи!!!

Beed Railway उद्घाटनासाठी Aji tPawar बीडमध्ये, Dhananjay Munde यांनी स्वागत केलं; मग जनता दरबार!

Beed Railway उद्घाटनासाठी Aji tPawar बीडमध्ये, Dhananjay Munde यांनी स्वागत केलं; मग जनता दरबार!

#आतली_बातमी Live: राष्ट्रवादीच्या घड्याळाला विलीनीकरणाची चावीच गरजेची? Ajit Pawar | Ashish Jadhao

#आतली_बातमी Live: राष्ट्रवादीच्या घड्याळाला विलीनीकरणाची चावीच गरजेची? Ajit Pawar | Ashish Jadhao

सोनकच्छ से ब्यावरा के बीच में कार्य कंप्लीट हुआ रामगंज मंडी भोपाल रेल लाइन

सोनकच्छ से ब्यावरा के बीच में कार्य कंप्लीट हुआ रामगंज मंडी भोपाल रेल लाइन

ДОСТОЕВСКИЙ: СЕКРЕТНЫЕ ДНЕВНИКИ о ЕВРЕЯХ! то что скрывали 140 ЛЕТ после смерти ГЕНИЯ!

ДОСТОЕВСКИЙ: СЕКРЕТНЫЕ ДНЕВНИКИ о ЕВРЕЯХ! то что скрывали 140 ЛЕТ после смерти ГЕНИЯ!

ODISHA NEW RAIL LINE LATEST update 2025 ECoR SER Mayurbhanj Jharkhand Talcher Bolangir Puri Bargarh

ODISHA NEW RAIL LINE LATEST update 2025 ECoR SER Mayurbhanj Jharkhand Talcher Bolangir Puri Bargarh

Live.. जिल्हा परिषद पंचायत समिती निवडणुकीच्या अनुषंगाने वडवळ येथून प्रचार शुभारंभ!

Live.. जिल्हा परिषद पंचायत समिती निवडणुकीच्या अनुषंगाने वडवळ येथून प्रचार शुभारंभ!

EastWest DFC Dedicated Freight Corridor 2024 update new rail train line Chhattisgarh map maharashtra

EastWest DFC Dedicated Freight Corridor 2024 update new rail train line Chhattisgarh map maharashtra

😍 बीड स्टेशन वर रेल्वे आली 16 September 2025 |  Beed Railway Station

😍 बीड स्टेशन वर रेल्वे आली 16 September 2025 | Beed Railway Station

Ahmednagar beed parli railway update.beed railway station| बीड परळी रेल्वे लाईन अपडेट| #beedrailway

Ahmednagar beed parli railway update.beed railway station| बीड परळी रेल्वे लाईन अपडेट| #beedrailway

Чиновник ШАРЛАПАЕВ во главе Палаты предпринимателей «АТАМЕКЕН» / Владимир ДВОРЕЦКИЙ. ГИПЕРБОРЕЙ №585

Чиновник ШАРЛАПАЕВ во главе Палаты предпринимателей «АТАМЕКЕН» / Владимир ДВОРЕЦКИЙ. ГИПЕРБОРЕЙ №585

Gujarat new rail line update 2025 Western Railway Ahemdabad Vadodara Bhavnagar Rajkot Coastal ports

Gujarat new rail line update 2025 Western Railway Ahemdabad Vadodara Bhavnagar Rajkot Coastal ports

जालना जळगांव रेलमार्ग मार्गासाठी ५१ गावांमध्ये भूसंपादन प्रक्रिया सुरू Jalna Jalgaon Railline Update

जालना जळगांव रेलमार्ग मार्गासाठी ५१ गावांमध्ये भूसंपादन प्रक्रिया सुरू Jalna Jalgaon Railline Update

ЭКСТРЕННЫЕ НОВОСТИ! СТАРИКОВ - ПРЯМОЙ ЭФИР! СЕГОДНЯ ОСТАНОВЯТ ВОЙНУ...

ЭКСТРЕННЫЕ НОВОСТИ! СТАРИКОВ - ПРЯМОЙ ЭФИР! СЕГОДНЯ ОСТАНОВЯТ ВОЙНУ...

Pune Ahmednagar Railline पुणे से अहिल्यानगर छोटा रेलमार्ग DPR पहुंची रेलवे बोर्ड,अंतिम स्वीकृति जल्द

Pune Ahmednagar Railline पुणे से अहिल्यानगर छोटा रेलमार्ग DPR पहुंची रेलवे बोर्ड,अंतिम स्वीकृति जल्द

Presenting the newest feather in our cap: The Khurda Road – Bolangir New BG Link Project

Presenting the newest feather in our cap: The Khurda Road – Bolangir New BG Link Project

Wardha–Nanded Railway Line Construction Progress Update from Nanded -  MPC

Wardha–Nanded Railway Line Construction Progress Update from Nanded - MPC

Тайминг встречи Зеленского и тайминг в Кремле! Дедлайн - весна! Запахло Миром? Удар по Украине

Тайминг встречи Зеленского и тайминг в Кремле! Дедлайн - весна! Запахло Миром? Удар по Украине

Beed Railway Special Report : बीड रेल्वेच्या ट्रॅकवर पहिली रेल्वे श्रेयवादाची, प्रकरण काय?

Beed Railway Special Report : बीड रेल्वेच्या ट्रॅकवर पहिली रेल्वे श्रेयवादाची, प्रकरण काय?