The proposed Activity would be to construct a new 1.64 km long skywalk and associated carpark, commencing near the north-western corner of Lot 7300 DP 1152789 and Lot 1 DP 1108482 and zig zagging in a south-eastern direction up to Oxley Scenic Lookout (refer to Plate 2.4 to Plate 2.7 and Illustration 2.1). The skywalk would consist of a combination of boardwalk, viewing platforms, and elevated walkway.
Construction Methodology
In summary, the works methodology is expected to be as follows:
■ Establish site and set up compounds.
■ Undertake clearing of identified vegetation.
■ Establish access tracks along route of structure.
■ Construct footings for boardwalks and bridge structures.
■ Install substructure and superstructure of walkways.
■ Install lighting and balustrades for skywalk.
■ Remove access tracks.
■ Complete finishing works for skywalk i.e. lighting and fixed furniture.
■ Revegetate area around skywalk.
■ Excavate, form, reinforce, and pour concrete footpath at the top of the walkways.
■ Demobilise top site compound (no rehabilitation required).
■ Excavate bottom carpark formation.
■ Construct new carpark.
■ Demobilise bottom site compound and topsoil disturbed area.