Development Update 21 | CBD Punjab
Автор: CBD Punjab
Загружено: 2023-02-19
Просмотров: 527
Описание:
Steel work on barrel portion (Ali Zeb Underpass), retaining wall and rigid pavement work on Kalma underpass, sump well work on Saint Mary’s Park, steel work for storm water drain (Infrastructure Phase-1) and excavation work on CBD Underpass is in progress.
CBD Punjab is overseeing all development activities to ensure their timely completion.
#CBDPunjab #CBDBoulevard #CBD #Development #Progress #Punjab