Polaris Forge 1 Campus Update | February 2026
Автор: Applied Digital
Загружено: 2026-02-27
Просмотров: 507
Описание:
February construction progress at Polaris Forge 1 continues with strong momentum.
More than 1,200 skilled craft professionals are advancing two 150 MW facilities in parallel at the campus.
Polaris Forge 1-2 (150 MW Critical IT Load):
• JWF Heat Rejection Modules from BASX are installed on the roof
• Main electrical equipment from ABB has been received, with terminations underway
• Tenant fit-out has begun in the data halls in preparation for turnover
Polaris Forge 1-3 (150 MW Critical IT Load):
• Precast structure is 25% complete
• Foundations are 85% complete
With trusted partners like McGough, ABB, and BASX, progress continues with confidence.
#PolarisForge #AIDataCenter #150MW #DataCenterConstruction #AppliedDigital