April 2025 Construction Update | MK One
Here's wishing you all a Happy Ugadi!
Here are the points covered in this month’s construction update:
• Tower D: All 25 floors and terrace amenities completed
• Tower C: Slab work completed; terrace amenities in progress
• Tower B: 22nd floor slab work in progress
• Tower A: 15th floor construction in progress
• Clubhouse: Exterior nearing completion; interior painting in progress
• Basement Levels: Flooring completed across all three levels
• Landscaping: Driveway landscape work has begun
Watch the full video to see how MK One continues to take shape.