A Harmonious Blend of Accessibility and Serenity I Construction Update RA1N
Автор: Object 1
Загружено: 2025-07-07
Просмотров: 338
Описание:
Construction at the RA1N project is active with continuous progress. Get the latest updates here:
RA1N Site progress:
1. Concrete work is done.
2. Block work is done.
3. Plaster work is done.
4. Waterproof is done.
5. Tile work 98%.
6. False ceiling 98%.
7. Aluminum frame 97%.
8. Painting work 88%.
9. Facade finishing works 85%.
10. Landscaping and swimming pool 45%.