Baseline Schedule Explained: What It Is & How to Build One in 10 Steps
Автор: TheFloatHunter
Загружено: 2026-10-27
Просмотров: 14
Описание:
How do you know you're 12 days late? Late compared to what? Every delay, claim and progress report needs one fixed reference point: the baseline schedule.
In this video, The Float Hunter explains what a baseline schedule is, what you need before you start, and the 10 steps to build one your client will approve, using a manufacturing plant as the example.
⏱️ CHAPTERS
0:00 What this video covers
0:11 Late compared to what?
0:22 What is a baseline schedule?
0:40 Why it matters
0:59 What you need before you start
1:22 Steps 1–3: WBS, activities, durations
1:40 Steps 4–6: logic, calendars, milestones
1:57 Steps 7–9: resources, critical path, quality check
2:13 Step 10: review, approve & freeze
2:29 Recap
2:42 A good baseline proves delays
📌 INPUTS YOU NEED
Contract & scheduling specification · Drawings, scope & quantities · Construction method · Resources & productivity rates · Procurement lead times · Work calendar · Client & third-party dates
📌 THE 10 STEPS
1. Break down the work (WBS)
2. List the activities
3. Estimate durations (quantity ÷ productivity)
4. Link the logic (no open ends)
5. Set the calendars
6. Add milestones, few hard constraints
7. Load resources & cost (if required)
8. Schedule & check the critical path
9. Run a quality check
10. Review, approve & freeze (P6: Maintain Baselines · MS Project: Set Baseline)
👍 Subscribe to The Float Hunter for simple, practical construction planning lessons.
💬 What's the hardest part of getting your baseline approved?
#baselineschedule #constructionplanning #scheduling #primavera #P6 #msproject #planningengineer #civilengineering #projectmanagement #criticalpath #thefloathunter