Project Progress December 2025
Автор: Alex Miquel
Загружено: 2026-01-19
Просмотров: 55
Описание:
During December and the beginning of the new year we have achieved important progress in some key project sites.
Work on the pipeline installation was completed which is now undergoing hydraulic pressure testing. Similarly, we finalized commissioning of the Costal Electrical system and both pumping stations 1 and 2 are now energized, as is the Desalination Plant.
Just before Christmas the two sections of the first of two intakes were launched from the assembly site in Tocopilla and towed with tugboats to the site, where there were sunk in their final position. Currently the last connections to both the sea water pumping pit, and the intake riser are being completed, with the target of commissioning te intake before ethe end of January.
With all of these works nearing final completion, commissioning of the desalination plant was started in early January.
We have now reached 94% completion of the project. As we fully transition into the commissioning phase of the project, we still face many challenges, but are confident that with the joint effort of our team of people at Aguas Horizonte and of our Owner's Engineer, in cooperation with our EPC Contractor, will soon start delivering water to our customer, Codelco.
Повторяем попытку...
Доступные форматы для скачивания:
Скачать видео
-
Информация по загрузке: