Agbodza Updates on Big Push Roads: Pokuase–Amasaman, Kasoa, Dawhenya, Eastern Corridor & More”
Автор: JoyNews
Загружено: 2025-09-04
Просмотров: 27068
Описание:
🚧 Ghana’s Roads Minister, Kwame Governs Agbodza, speaks extensively on the status of critical Big Push road projects across the country, including Pokuase–Amasaman, Kasoa–Winneba, Dawhenya, Adenta–Dodowa, Dawhenya, Eastern Corridor, Kumasi interchanges, and more.
Key highlights:
🔴Pokuase–Amasaman Road:
• Total contract sum: $346m
• Over $273m already paid (≈75% complete)
• Contractor commits to completion by April 2026
🔴Adenta–Dodowa Road: Contractor mobilizing; expected to fall under Big Push (≈24-month timeline).
🔴Dawhenya Road: Work stalled by BHM, now split with First Sky to handle the main carriageway, while BHM handles service roads/interchanges.
🔴Kasoa–Winneba Road: Lessons learned after both sides were closed simultaneously; new stretches to adopt a different strategy.
🔴Eastern Corridor Road: Sections stalled, but now absorbed under Big Push, with China Jiangxi set to handle Asa-Ho stretch.
🔴Kumasi Interchanges (Santasi, Suame, Sofoline): Funding challenges due to debt restructuring, but part of Big Push rollout.
🔴Ho–Adomi–Aflao stretch: Six-lot segmentation, contractors mobilizing this year.
🔴National Roads Dashboard: Ministry plans a public platform to track contracts, payments, and road statuses with citizen feedback.
The Minister stressed that unlike past governments, the current administration has not suspended contractors’ work after taking office, instead opting to encourage continuity and prioritize payments.
Chapters:
00:00 – Pokuase–Amasaman payments explained ($195m earlier, $77m under current gov’t)
05:39 – Remaining balance under $100m; Big Push to cover gap
06:47 – Project 75% complete
08:55 – Adenta–Dodowa road status & new connections
12:25 – Dwinia Road: BHM vs. FesKai roles
18:35 – Clarification on main carriageway vs. service roads
19:32 – Ho–Adomi–Aflao corridor updates
21:11 – Kasoa–Winneba road works & new strategy
23:06 – Eastern Corridor status (Asa–Ho, Ho–Dambai, etc.)
25:14 – Dambai & Adawso bridges procurement
25:56 – Kumasi interchanges (Santasi, Suame, Sofoline) update
28:57 – Road Fund debts ($7bn+) & questions on “Year of Roads”
30:47 – Plans for a Roads Dashboard for transparency
#MyJoyOnline
#JoyNews
https://www.myjoyonline.com/ghana-news/
Subscribe for more videos just like this:
/ @myjoyonline
Follow us on: Facebook: / joy997fm
Twitter: / joy997fm
Instagram: https://bit.ly/3J2l57
Повторяем попытку...
Доступные форматы для скачивания:
Скачать видео
-
Информация по загрузке: