Barapullah Flyover Phase 3 Update | To be Open in September 2026 | Delhi PWD
Автор: OMW Infra
Загружено: 2026-09-01
Просмотров: 58440
Описание:
Barapullah Flyover Phase 3 Update | Delhi's Longest Delayed Flyover Project | Complete History of Phase 1, 2 & 3
The Barapullah Flyover is one of Delhi's most important urban infrastructure projects, designed to provide a signal-free corridor between East Delhi, Central Delhi, and South Delhi. Originally developed for the 2010 Commonwealth Games, the project has expanded in multiple phases over the years.
Phase 1: Commonwealth Games Corridor
Barapullah Phase 1 was constructed before the 2010 Commonwealth Games to connect Sarai Kale Khan with Jawaharlal Nehru Stadium. This elevated corridor significantly reduced travel time between East Delhi and Central Delhi while easing congestion on major roads.
Phase 2: Extension Towards INA
The second phase extended the flyover from Jawaharlal Nehru Stadium to INA and AIIMS areas. Opened in stages, this extension improved connectivity between South Delhi and Central Delhi and became a crucial route for daily commuters.
Phase 3: The Missing Link
Barapullah Phase 3 is the most challenging and delayed part of the project. It aims to connect Mayur Vihar Phase-1 in East Delhi with the existing Barapullah corridor near Sarai Kale Khan, creating a seamless signal-free route from East Delhi to South Delhi.
The project includes:
• Multiple elevated flyovers and ramps
• New bridges over railway lines and drains
• Direct connectivity between Mayur Vihar, Sarai Kale Khan, INA and AIIMS
• Reduction in travel time for lakhs of commuters every day
Why Was Phase 3 Delayed?
Barapullah Phase 3 has faced numerous hurdles over the years, including:
• Land acquisition issues
• Utility shifting challenges
• Forest and environmental clearances
• Coordination with Railways
• Contractor-related delays
• COVID-19 pandemic disruptions
These challenges turned what was expected to be a relatively quick project into one of Delhi's longest-running flyover constructions.
Project Cost
The cost of the project has increased significantly over time due to delays, revised designs, inflation, and additional construction requirements.
Expected Benefits After Completion
Signal-free travel from Mayur Vihar to South Delhi
Reduced congestion on Ring Road and surrounding corridors
Faster access to AIIMS, INA, Sarai Kale Khan and Central Delhi
Improved connectivity for East Delhi residents
Reduced fuel consumption and travel time
In this video, we take a detailed ground report of the latest construction progress, pending works, remaining challenges, and the expected timeline for completion of Delhi's much-awaited Barapullah Phase 3 project.
If you enjoy infrastructure, highways, metro projects, expressways and urban development updates, don't forget to Like, Share and Subscribe to OnMyWay Infra.