Here's a summary of the progress of the Hannam 2 District Redevelopment Project (Hannam-dong and Bogwang-dong, Yongsan-gu, Seoul) as of February 2026. Based on recent news and current developments, the project is proceeding as planned, but some scheduling and cooperative issues remain.
Daewoo E&C Collaborates with Global Architect for 'Roppongi Hills' in Hannam 2 District
Daewoo E&C Collaborates with US-based Judd for Hannam 2 District...Participates in Detailed Design
January 20
🔎 1. Approval of Management and Disposition Plan and Full-Scale Project Launch
🟡 Approval of Management and Disposition Plan (Project Implementation Details)
In 2025, the Yongsan District Office finally approved the management and disposal plan for the Hannam 2 District Redevelopment Project,
and this completes the legal foundation for the project to begin in earnest.
📍 Key Approval Details
31 buildings, totaling 1,537 units
Includes cooperative members (986 units), general sale units (292 units), rental housing, and other units.
Top-Ranking Business Newspaper Financial News
The project will proceed in the following order: relocation → demolition → commencement of construction.
🔜 Relocation Schedule
Relocation (resident eviction) could begin around October 2025,
and demolition and construction will commence in earnest once residents are relocated.
➡️ Relocation has actually begun since late 2025, and preparations for relocation and demolition are likely to continue into early 2026 (some reports mention controversy surrounding relocation preparations and the lending group).
🏗️ 2. Design and Construction Progress
🟢 Design Upgrades
Reports indicate that Daewoo E&C held a meeting with JERDE, a global US design firm, in January 2026 to further enhance the complex design.
⚠️ Construction Company Issues
Some union members have reportedly expressed dissatisfaction with the formation of a lending group, securing additional relocation funds, and concerns about the construction company's re-establishment or conflicts.
This has raised concerns about potential adjustments to the project schedule.
(※ Lender Group: A group of lending institutions the union contracts with, including financial institutions, and plays a key role in securing relocation and construction costs.)
🛠️ Willingness to Proceed with the Redevelopment Project
Yongsan-gu Mayor Park Hee-young visited the site in 2026 and reaffirmed his commitment to redevelopment, emphasizing "speed and safety."
📅 3. Summary of Overall Project Flow
Progress (as of February 2026)
Stage
Project Implementation Approval
Completion (2021)
Management and Disposal Plan Approval
Completion (2025)
Relocation
Ensuing late 2025 - ongoing from 2026
Demolition
Planned to commence in earnest after relocation
Construction
Planned to commence after demolition
Completion
Still several years remaining
👉 Currently, the project is in the "Management and Disposal Plan Approval → Resident Relocation in Progress → Demolition Preparation/Commencement" phase. However, some internal issues within the cooperative and administrative procedures, such as the formation of a major shareholder group, may impact the future schedule.
🏘️ Note: Relationship with Surrounding Projects
Hannam New Town itself is divided into several districts, and while Hannam Districts 3 and 5 are actively undergoing redevelopment, Hannam District 2 has been relatively behind schedule.