Asphalt Core Underway at Chimney Hollow Reservoir
Автор: Northern Water
Загружено: 2022-10-24
Просмотров: 7460
Описание:
Chimney Hollow Reservoir construction crews hand-placed the first section of asphalt on the main dam on Oct. 15, 2022. Going forward, the asphalt will be placed 10 inches per lift along the concrete plinth, which serves as the base of the dam, until the dam reaches a height of about 350 feet. Rockfill is occurring concurrently to stabilize the asphalt core and will cover the plinth.
Once completed, Chimney Hollow Reservoir will be one of about 200 asphalt-core dams worldwide, only the second built in the U.S, and by far the tallest asphalt-core dam in the country.