Lake Turkana Power project by Bolloré Transport & Logistics
Автор: Bolloré Transport & Logistics
Загружено: 2017-06-21
Просмотров: 14110
Описание:
The delivery of 365 Wind Turbine Generators at the Lake Turkana Wind Power Project has been completed. Bolloré Transport & Logistics Kenya subsidiary which was contracted to provide customs clearance and logistics services for the Lake Turkana Wind Power Project transported 365 Wind Turbine Generators in 360 days, 5 days before the scheduled completion date.
The project, which began in March 2016, involved customs operations, vessel discharge and transportation of wind turbine generators from the port of Mombasa to the project site in Loyangalani District, Marsabit West County, located 1,220 km from Mombasa.